Skip to main content

Current & Upcoming Piping & Other Important Projects

Piping our old, leaky canals is an ongoing effort here at Swalley. Every year we try to round up the funding and partnerships to put as much pipe as we can in the ground. Piping projects allow water to be conserved for the natural environment, delivered more reliably to our customers, and utilized more efficiently on the land.

May contain: apparel, clothing, helmet, person, human, hardhat, accessories, sunglasses, and accessory
Swalley GM Jer Camarata & previous DRC CFO Bill Caram on a project inspection. The DRC, along with the USDA-NRCS, OWEB, ETO, and FCA are valuable community partners and project funders. We would also like to thank the Alice C. Tyler Charitable Trust and the Oregon Environmental Council for their generous support towards our restoration efforts.

 

Current Projects

No large construction projects are presently in the que for the 2021-2022 winter maintenance season (November - March) due to grant funding limitations. The District will be focusing on maintenence of existing facilities, screening improvements, and design engineering of future pipeline projects during this time period.

 

Future Upcoming Projects

-Main Lateral Piping Project Phase 7 (there are 10 phases total and we are currently complete through Phase 6) : This is an ~1.3 mile canal to large pipeline conversion project running north and adjacent to Hwy 97 up to Sunbeam Lane. The project is federally approved, but funding is still being sought and applications thereof are pending. Design engineering is in the early phases of development. Tentative construction dates are presently targeted for November 2023 - April 2024, but are subject to change based on funding availability.

 

Pending Projects

-Elder Lateral Piping Project: This is an ~2 mile long canal to pipeline conversion project in the heart of Swalley. The project is federally approved and permitted, but full funding for the project is being sought.  Engineering design on this project is at ~98+%. This project was originally slated for 2021-2022 construction, but funding limitations put a halt to the project going to bid. If funding issues are resolved, it is possible that the project could be back in line for construction during the 2023-2024 or 2024-2025 construction seasons.

-Main Lateral Piping Project Phase 8 : This is an ~1.3 mile canal to large pipeline conversion project. The project is federally approved and permitted, but full funding is pending. Design engineering has not occured.

-Butte Lateral Piping Project: This canal to pipeline conversion project is also in the heart of Swalley and generally runs west to east for ~1 mile adjacent to Tumalo Rd. The project is federally approved and permitted, but only partially funded at this time. State grant match dollars are actively being sought after being awarded and then lost due to state bond sale failures as a result of the coronavirus-based budget shortfalls at the state level. Design engineering has not occured.

-Main Lateral Piping Project Phase 9: This is an ~2 mile canal to large pipeline conversion project. The project is federally approved, but funding is pending. Design engineering has not occured.

-Main Lateral Piping Project Phase 10 (FINAL PHASE) : This is an ~2 mile canal to large pipeline conversion project. The project may also include the installation of a 400HP booster pump. The project is federally approved, but funding is pending. Design engineering has not occured.

 

Recently Completed Projects

-Rogers & Rogers Sub-Lateral Pipeline Project; 2019-2020. This major canal to pipeline conversion project started near Cooley Rd and generally ran north for ~3 miles adjacent to the Old Bend-Redmond Highway. The project included the Rogers Sub-Lateral which ran northeasterly ~1/4 mile from Cooley Rd to the Hunnel Rd vicinity. The project began October, 2019 and was substantially completed by March, 2020. The new pipeline went fully operational April 1, 2020, and came in on budget and on schedule for the 2020 Irrigation Season. The project included upgrading 43 on-farm turnout deliveries to state-of-the-art valved and metered deliveries. Conserved water benefitted the middle Deschutes River.

Restoration Status: While the pipeline project is substantially complete and operational, native seed drilling over the District's easement will occur during Fall, 2020 for those landowners that do not wish to plant their own land during the 2020 Irrigation Season. Restoration activities are typically ongoing and could last for several years.

May contain: pipeline
Aerial lift of a 20" section of Rogers Lateral HDPE Pipeline. The contractor was Taylor NW of Bend, OR

 

-Riley-Sub Lateral Pipeline Project; OB Riley Rd. Phase; Winter 2018-2019. This project converted 1/3 of a mile of roadside canal to a 24" to 18" HDPE pipeline. The project was in cooperation with the Bend-LaPine School District and was primarily a public safety project. The project exemplifies contemporary irrigation piping methods and technology through an urbanized environment. The new irrigation line utilizes state of the art water metering equipment. School ballfields and landscaping will use our irrigation water as a greener and cheaper alternative than potable city water.

May contain: human, person, and fireman
2018-2019 Riley Sub-Lateral Pipe welding

-Riley Lateral Pipeline Project.; Hardy Rd Development Phase; Winter 2017-2018

The Riley Lateral Pipeline along OB Riley and Hardy roads just behind the North Bend Fire Station was a joint 2016-2017 project between Swalley and a private developer. The canal was converted into a pipeline so that new road, water, and sewer infrastructure could be installed to 16 new homes. The project was paid for using all private funding, including a 1/3 financial contribution (including labor and equipment) from Swalley.

Finished landscaping over the pipeline was designed by a local landscape architect and is a local precedent for how nice-looking properly designed urban pipeline landscape coverings can be. The project is available for touring upon request.