Skip to main content

Current & Upcoming Piping Projects

Piping our old, leaky canals is an ongoing effort here at Swalley. Every year we try to round up the funding and partnerships to put as much pipe as we can in the ground. Piping projects allow water to be conserved and utilyzed more efficiently.

 

Current Projects

Winter 2023 through Spring 2026: During this time period the District will be engaged in several major transportation and commercial development construction activities including the ODOT Bend North Corridor and Costco Projects. The projects require modifications to major elements within the District's conveyance system and the piping of canals. The District continues to work on design-engineering and fundraising for the next phases of it's System Improvement Plan which aims to convert an additional several miles of open canals into buried pipelines north of the City of Bend. Please contact Swalley's general manager if you have any questions about any specific projects.

May contain: pipeline
The "New Costco" Canal-Piping Project -- 1/1/2024
May contain: pipeline
Rogers/Riley Relocation Project --  BNC 2023
May contain: helmet, shoe, footwear, clothing, person, and glove
Rogers/Riley Relocation Project --  BNC 2023

 

Upcoming Projects

-Main Canal Piping Project Phase# 7 (MC-7) (The Main Canal Piping Project consists of 10 phases total. The District is currently complete through Phase# 6) : The MC-7 is an ~1.3 mile canal-to-large (48"-42" diameter) pipeline conversion project that begins approximately 3 miles north of the City of Bend, runs adjacent to Hwy 97, and ends near Sunbeam Lane in Deschutes County. The project is designed, approved, and fully permitted. Tentative construction dates are now targeted for November 2024 - April 2025.

May contain: helmet and person
Loading 24" HDPE into the welder -- 2024

 

Pending Projects

-Elder Lateral Piping Project: This is an ~2 mile long canal-to-pipeline conversion project in the heart of Swalley. The project is federally approved and permitted. Only partial funding has been secured. Engineering design on the project is at ~98+% and on hold.

-Main Lateral Piping Project Phase# 8 : This is an ~1.3 mile canal-to-large pipeline conversion project. The project is federally approved and permitted. Funding is pending. Design engineering has not occured.

-Butte Lateral Piping Project: This canal-to-pipeline conversion project is also in the heart of Swalley and generally runs west to east for ~1 mile adjacent to Tumalo Rd. The project is federally approved and permitted. Funding is pending. Design engineering has not occured.

-Main Lateral Piping Project Phase# 9: This is an ~2 mile canal-to-large pipeline conversion project. The project is federally approved and permitted. Funding is pending. Design engineering has not occured.

-Main Lateral Piping Project Phase# 10 (FINAL PHASE) : This is an ~2 mile canal-to-large pipeline conversion project. The project is federally approved and permitted. Funding is pending. Design engineering has not occured.

 

Recently Completed Projects

May contain: apparel, clothing, helmet, person, human, hardhat, accessories, sunglasses, and accessory
Swalley GM Jer Camarata & previous DRC CFO Bill Caram on a project inspection. The DRC, along with the USDA-NRCS, OWEB, ETO, and FCA are valuable community partners and project funders. We would also like to thank the Alice C. Tyler Charitable Trust and the Oregon Environmental Council for their generous support towards our restoration efforts.

-Rogers & Rogers Sub-Lateral Pipeline Project; 2019-2020. This major canal to pipeline conversion project started near Cooley Rd and generally ran north for ~3 miles adjacent to the Old Bend-Redmond Highway. The project included the Rogers Sub-Lateral which ran northeasterly ~1/4 mile from Cooley Rd to the Hunnel Rd vicinity. The project began October, 2019 and was substantially completed by March, 2020. The new pipeline went fully operational April 1, 2020, and came in on budget and on schedule for the 2020 Irrigation Season. The project included upgrading 43 on-farm turnout deliveries to state-of-the-art valved and metered deliveries. Conserved water benefitted the middle Deschutes River.

May contain: pipeline
Aerial lift of a 20" section of Rogers Lateral HDPE Pipeline. The contractor was Taylor NW of Bend, OR

 

-Riley-Sub Lateral Pipeline Project; OB Riley Rd. Phase; Winter 2018-2019. This project converted 1/3 of a mile of roadside canal to a 24" to 18" HDPE pipeline. The project was in cooperation with the Bend-LaPine School District and was primarily a public safety project. The project exemplifies contemporary irrigation piping methods and technology through an urbanized environment. The new irrigation line utilizes state of the art water metering equipment. School ballfields and landscaping will use our irrigation water as a greener and cheaper alternative than potable city water.

May contain: human, person, and fireman
2018-2019 Riley Sub-Lateral Pipe welding

-Riley Lateral Pipeline Project.; Hardy Rd Development Phase; Winter 2017-2018

The Riley Lateral Pipeline along OB Riley and Hardy roads just behind the North Bend Fire Station was a joint 2016-2017 project between Swalley and a private developer. The canal was converted into a pipeline so that new road, water, and sewer infrastructure could be installed to 16 new homes. The project was paid for using all private funding, including a 1/3 financial contribution (including labor and equipment) from Swalley.

Finished landscaping over the pipeline was designed by a local landscape architect and is a local precedent for how nice-looking properly designed urban pipeline landscape coverings can be. The project is available for touring upon request.